In my work as a construction-defect expert witness, I see a certain problem in the design and construction of spillways all too frequently: When the system is initiated, the flow of water down the face of the dam wall will behave more or less as desired, holding to a narrow path into the pool or trough that awaits it. After a time, however, that water will begin to migrate, spreading out farther and farther beyond the desired pathway until the material – usually some sort of brick or stone – builds up scale and starts looking awful as the situation advances.

This time, I’ll report on a situation in which the consequences of the water migration were basically aesthetic. Next time, I’ll look at a case in which the water traveled in such a way that it actually did significant damage.

The scenario: A project I was asked to investigate had a classic water-migration issue: The water was set up to spill from one level to another in such a way that it flowed down the face of the wall instead of pushing past the wall’s surface via some sort of extension that would let it drop directly into the pool without hugging the wall. (This can be particularly problematic with stacked stone, which creates easy horizontal planes along which the water can flow.)

When the water first started flowing in this spillway, it rolled down the face of the ledgerstone dam wall and more or less directly into the pool. Almost immediately, however, it began broadening its path to include adjacent sections of wall – and finally a step that started looking awful in rapid order.

The fix: Clearly, what happened here was that the stone’s surface had little or no ability to serve as a limiting vertical channel for the water. Water being water, in other words, it found other paths by trickling sideways and wicking onto surrounding surfaces.

Getting rid of this problem, unfortunately, requires anticipating it by including a vertical break in the finish that will encourage the great majority of the water to flow in the desired downward direction.

In the project shown in the photograph at left, for example, a vertical break was planned and built right into the wall system. It doesn’t need to be big to be effective: A half inch gap or less will do the job of directing the majority of the migratory flow directly down into the pool or trough. And to be on the safe side, treating the gap with a silicone sealant will keep the far side of the channel from becoming an eventual pathway (however minor) for traveling water.

To be sure, this solution has aesthetic consequences and might provide an unwelcome visual break in some situations, but it will eliminate most of the worsening appearance presented by water migration. In fact, this might even be an essential, unavoidable step with horizontally oriented finish materials, such as ledgerstone or brick.

And don’t overlook the possibility of designing such spillways with a protruding edge that directs the water out past the wall. The flow rate must be fairly robust, and some water will find its way to the wall, but this may be the best way to reduce migrating-water issues.

Lesson Learned: Water seldom follows only those paths you want it to follow, and the key to avoiding the problems it presents when it migrates is to accept the immediate challenge and give it an easier way to flow where you want it to go, either by using a baffle or vertical break – or focusing on a better spillway design.

Share this article:

Facebook
Twitter
LinkedIn
Recent Articles
Acrylic sphere water feature with integrated LED lighting designed by Scott Cohen & The Green Scene

Sculpture on the Side

In this WaterShapes feature, Scott Cohen uses The Green Scene’s PHTA award-winning “Side Hustle” project to show how an overlooked side yard can become one of a property’s most distinctive spaces. He covers working with tight site constraints instead of against them, layering hardscape, water, light and planting to add depth without adding footprint, and designing for sound and atmosphere as much as looks. His conclusion: good watershape design isn’t always about going bigger, but about making a small space matter more.

Read More »
California Business and Professions Code section 7159

What Must Be Included in a California Home Improvement Contract?

Many California home improvement contracts fail to meet the state’s strict legal requirements — and the consequences can be severe. Drawing on more than 24 years as a CSLB Industry Expert, this guide breaks down the 19 elements every compliant contract must include, from proper font sizes to swimming pool project disclosures, and explains why a defective contract can leave a contractor unable to collect payment.

Read More »
Illustrated construction crew at a home build site, with a foreman in a hardhat holding blueprints and a clipboard in the foreground, surrounded by tradespeople including an electrician, plumber, excavator operator, safety inspector, mason, and landscaper, representing the subcontractors covered under California's 2026 disclosure law.

California’s New 2026 Subcontractor Disclosure Requirement

Starting January 1, 2026, California home improvement contracts must disclose whether subcontractors will be used on a project — and if so, provide their names, license numbers, and classifications upon request. SB 517’s amendment to Business and Professions Code section 7159 adds new Yes/No disclosure boxes to contracts and change orders. Contractors still using pre-2026 templates risk CSLB discipline — and for pool contracts specifically, non-compliance can render the agreement void and unenforceable.

Read More »

Contact Scott Cohen