Planning for a Rainy Day

In most backyard swimming pool projects, we install the drainage systems for decks after the swimming pool’s plumbing, basically because the pool plumbers use big trenchers that will likely destroy the small drainage plumbing if it’s already in place.

That sequencing, combined in one instance with bad timing and a minor lapse in common sense, led to an enormous problem in one of our recent projects. It happened in a side yard where the plumber had just dug trenches for the pool’s lines but we had yet to address issues of sheet-flow and rainwater drainage.

Scenario: As bad luck would have it, the evening after those big trenches were dug, the skies opened up with unusually torrential rainfall. Not only was the side yard completely unprepared for rain, but also the trenches and the spoils dramatically aggravated the problem because the trenches were oriented in such a way that they blocked the water’s exit from the yard.

Hindsight is 20/20, but basically, when you dig a trench and then pile up the spoils beside it for later removal, you might inadvertently be creating an absolutely perfect structure for making sure water stays right where it is. In our case, the trenches collected the water, caused it to stop flowing and enabled it to saturate the ground as well as the linear pile of dirt, making it act like a dam.

The impromptu pond that formed in the middle of the night was bounded on one side by an exterior living room wall. Topping it all off, the living room was recessed inside the house: It’s floor sat right on grade, forming the lowest point in the house.

Early the next morning, we received a call from the client letting us know that there was an inch of water in the living room. It had flowed up through the weep screed, over the foundation and into the walls, ruining the carpet and damaging some very nice, very expensive furniture.

This is, of course, the kind of thing that will upset even the most temperate of clients — and will set emotional ones into states of pure panic. In this case, the clients were cool people who let us work out the problem in ways that involved minimal hassle.

We acted quickly, ripping out the carpet and carting it away. We then dried the floor and cut away the bottom two feet of drywall the length of the room to let it dry out. After spraying the wood structure with bleach to prevent mold and bringing in a mold-remediation specialist to test our work, we let everything dry before reinstalling the drywall, painting the room and replacing the carpet. Happily, the furniture was fine once we dried and cleaned it.

Frankly, we got off easy on this one, thanks mainly to quick action and our good relationship with the client. In other situations, I could imagine the remediation costing several times what it did in this situation.

Later on, I had an animated conversation with the plumber about what had happened. He refused to take any responsibility for what took place, but to this day I’m convinced he was to blame.

The Fix: Preventing this problem is as easy as being aware that trenching can cause flooding when it rains, and that you need to be sure to give water a place to go whenever and wherever it might accumulate. For the most part, all it takes is cutting a small channel or deploying sandbags that will allow the water to keep flowing away from the disturbed area.

In this case, we cut a line perpendicular to the house that trapped the water. We should have known better and definitely should have cut a short trench parallel to the wall of the house that would’ve allowed the water to flow away from the building. It’s as simple as that: A few minutes’ labor would have saved us thousands of dollars.

Most contractors live and die by the weather and are always thinking about protecting dry materials or a fresh excavation or newly poured concrete when storm clouds gather. Given the fact that this rainy-day thinking is part of what we all do anyway, I’d say thinking through such drainage issues is just another item to add to our internal punch lists.

Lesson Learned

Although this applies to just about everything we’re covering in this series of “Lessons Learned,” preventing flooding boils down to learning from your mistakes (or, better yet, from the mistakes of others), communicating with staff and subcontractors, and taking the necessary steps to make sure bad things don’t happen. Literally, it all breaks down to planning for a rainy day!

Share this article:

Facebook
Twitter
LinkedIn
Recent Articles
Acrylic sphere water feature with integrated LED lighting designed by Scott Cohen & The Green Scene

Sculpture on the Side

In this WaterShapes feature, Scott Cohen uses The Green Scene’s PHTA award-winning “Side Hustle” project to show how an overlooked side yard can become one of a property’s most distinctive spaces. He covers working with tight site constraints instead of against them, layering hardscape, water, light and planting to add depth without adding footprint, and designing for sound and atmosphere as much as looks. His conclusion: good watershape design isn’t always about going bigger, but about making a small space matter more.

Read More »
California Business and Professions Code section 7159

What Must Be Included in a California Home Improvement Contract?

Many California home improvement contracts fail to meet the state’s strict legal requirements — and the consequences can be severe. Drawing on more than 24 years as a CSLB Industry Expert, this guide breaks down the 19 elements every compliant contract must include, from proper font sizes to swimming pool project disclosures, and explains why a defective contract can leave a contractor unable to collect payment.

Read More »
Illustrated construction crew at a home build site, with a foreman in a hardhat holding blueprints and a clipboard in the foreground, surrounded by tradespeople including an electrician, plumber, excavator operator, safety inspector, mason, and landscaper, representing the subcontractors covered under California's 2026 disclosure law.

California’s New 2026 Subcontractor Disclosure Requirement

Starting January 1, 2026, California home improvement contracts must disclose whether subcontractors will be used on a project — and if so, provide their names, license numbers, and classifications upon request. SB 517’s amendment to Business and Professions Code section 7159 adds new Yes/No disclosure boxes to contracts and change orders. Contractors still using pre-2026 templates risk CSLB discipline — and for pool contracts specifically, non-compliance can render the agreement void and unenforceable.

Read More »

Contact Scott Cohen